The progress is moving quickly on the church lot! Today, we sat and watched the West wall being lifted up and placed in position! Rafters are also beginning to come in sight! I will post pictures of that tomorrow. Pretty soon, we wont be able to monitor the progress of the building because it will be all interior work! None the less, it is all progressing on schedule.
BRANCH PRESIDENCY UPDATE:
(posted in the Sacrament Meeting Program on August 22nd, 2010)
The following tasks have been completed: site preparation, foundation, below the floor plumbing, under floor fill, concrete floor, and backfill. This week the contractor poured the concrete floor and began installing wall framing. Construction is progressing on schedule. Now that the work is above ground it is easier to see progress and it seems to go faster. (Reminder that no one is allowed on the construction site without invitation from the general contractor).